Environmental Issues
Public registers
POEO Public Register
Licences, applications and notices search
Penalty notices search
Enforceable undertakings search
Enforceable undertakings media releases
Exemptions and approvals search
Prosecutions or civil proceedings search
Terms of use: POEO public register
Licensing FAQs
List of licences
Unlicensed premises regulated by the EPA
Contaminated land record of notices
About the record of notices
List of notified sites
Tips for searching
Disclaimer
Dangerous goods licences
Pesticide licences
Radiation licences
Home
Public registers
POEO Public Register
Licences, applications and notices search
Non-Compliance detail
Summary
Licence number:
2148
Annual Return Start:
21 Jul 2012
Annual Return End:
20 Jul 2013
Date Received:
19 Sep 2013
Licence Condition number
Type of non-compliance
EPA actions
No. of times occurred
L2.4
Treatment Plant discharged without de-chlorination due to value not fully closed which impeded performance. Manual isolation valve shut upstream. Design review of Treated Water discharge system conducted. Low flow detection device installed.
Penalty Notice issued
1
M2.3
Conductivity probe offline causing treated water discharge due to loose connection @ Point 15 probe, possibly caused by Electrical/Instrumentation technicians working in area. Pollutants in Treated Water measured at levels below licence limits.
Appropriate Action taken by licensee
1
M4.1
Point 12 weather station offline due to lightning strike on Botany Industrial Park, duration 2 hrs 45 minutes. No adverse effects resulted from incident. As interim measure GTP operators recorded data from BofM weather station @ Sydney Airport.
EPA to monitor future compliance with this condition
1